Work on Cal Poly’s new Center for Science and Mathematics is moving forward, with completion targeted for May 2013.
Work on Cal Poly’s new Center for Science and Mathematics is moving forward, with completion targeted for May 2013. jjohnston@thetribunenews.com

Work on Cal Poly’s new Center for Science and Mathematics is moving forward, with completion targeted for May 2013.

The latest progress includes the following: Masonry is 70 percent complete; elevators inside are running; interior framing is about 80 percent done; roofing is 75 percent complete; and work on sidewalks, stairs and landscaping will begin in the fall.

Most of the funding for the $119 million project, headed by San Diego-based Gilbane Building Company, came from a state general obligation bond approved by voters. Roughly $18 million is from private funds raised by the university.