Hearing on request to increase Los Osos sewer project's budget is postponed

nwilson@thetribunenews.comJanuary 2, 2014 

The San Luis Obispo County Board of Supervisors has postponed hearing a request for approval to increase the budget for the Los Osos Wastewater Project by about $4.3 million.

The request proposes adding about $2.8 million to a contract with HDR Engineering for construction management services, increasing the agreement from $6.8 million to $9.7 million.

The board also delayed a decision on approving an additional $1.4 million in design costs for Carollo Engineers, revsing that contract upward to $4.8 million.

The board directed the staff to bring the item back for discussion sometime in January after some residents complained that the item appeared on the Dec. 17 consent agenda without detailed examination.

The date for the rescheduled discussion has not yet been set.

The Tribune is pleased to provide this opportunity to share information, experiences and observations about what's in the news. Some of the comments may be reprinted elsewhere in the site or in the newspaper. We encourage lively, open debate on the issues of the day, and ask that you refrain from profanity, hate speech, personal comments and remarks that are off point. Thank you for taking the time to offer your thoughts.